• Home
  • Contact Us
  • Privacy Policy
Tuesday, August 25, 2026
The Atlas Malawi
  • Home
  • National
  • Education
  • Health
  • Features
  • Politics
  • News
    • Business
  • Entertainment

    Lucius Banda Mausoleum unveiling Saturday in Balaka

    A Million eyes watching but no bread on the table: Malawi’s creators harvesting likes but reaping poverty

    NBM supports ‘Onesimus vs Armstrong’ concert with K5m

    Standard Bank hikes ATEM sponsorship to K35m

    Dalitso Chaponda leaves Malawi in stitches with electrifying farewell show

    EU Delegation, Music Crossroads Malawi to celebrate young musicians at 2025 Directors’ Merit Awards

  • Sports
No Result
View All Result
  • Home
  • National
  • Education
  • Health
  • Features
  • Politics
  • News
    • Business
  • Entertainment

    Lucius Banda Mausoleum unveiling Saturday in Balaka

    A Million eyes watching but no bread on the table: Malawi’s creators harvesting likes but reaping poverty

    NBM supports ‘Onesimus vs Armstrong’ concert with K5m

    Standard Bank hikes ATEM sponsorship to K35m

    Dalitso Chaponda leaves Malawi in stitches with electrifying farewell show

    EU Delegation, Music Crossroads Malawi to celebrate young musicians at 2025 Directors’ Merit Awards

  • Sports
No Result
View All Result
No Result
View All Result
Home National

EGENCO allocates USD8.1m towards addressing power generation challenges 

Mana by Mana
August 24, 2026
in National
0
EGENCO allocates USD8.1m towards addressing power generation challenges 
Share on FacebookShare on Twitter

By Prisca Promise Mashushu:  

The Electricity Generation Company (Malawi) Limited (EGENCO) has assured Malawians that it is addressing challenges affecting power generation in the country with about USD8.1 million allocated towards procurement of spare parts for the faulty power plants.

In a statement issued on Monday, EGENCO says all its hydropower generation units are operational, except Nkula B Unit 6, which has developed a technical fault and is currently out of service.

You might also likePosts

NOCMA loses K700m to email scam

NOCMA loses K700m to email scam

August 24, 2026
HRCC calls for review of Malawi’s forfeiture laws 

HRCC calls for review of Malawi’s forfeiture laws 

August 21, 2026
Global Fund selection row deepens as members reject post-meeting votes

Global Fund selection row deepens as members reject post-meeting votes

August 21, 2026

The EGENCO management says its workforce is working diligently to restore affected generation units and strengthen the Malawis power supply.

“Government has been very supportive that almost USD8.1 million has been allocated for spares acquisition. We have since paid for the most critical spares through such support,” reads the statement in part.

The statement says Nkula A Power Station is currently generating 24 megawatts (MW) against its installed capacity of 35.1MW due to worn-out turbine shaft seals, while Tedzani Units 5 and 6 are operating at a combined reduced capacity of 5MW due to debris and stones accumulating at the intake following the impact of Cyclone Ana in 2022.

“Most of these challenges have arisen due to delays in the procurement of critical spare parts over the past two to three years due to forex constraints,” reads the statement in part.

EGENCO further says it has put measures in place to restore full generation capacity, including working around the clock to return all affected machines to full operational capacity.

On Nkula B Unit 6, which has a generation capacity of 20MW, EGENCO says damaged generator bearing parts, including the shaft, are being dismantled and will be transported to the Original Equipment Manufacturers workshop in South Africa for repairs.

“The Government of Malawi, through the Reserve Bank, has allocated foreign exchange for the procurement of the required spare parts. As of July 2026, all spare parts had been fully paid for, manufactured and are currently being shipped into the country to arrive in September 2026,” reads the statement.

The statement adds that the affected units are expected to return to their full generation capacity by the end of September 2026 upon completion of the repairs.

On Tedzani Units 5 and 6, the company says it had engaged a contractor to remove debris and stones from the intake area and was mobilising equipment for the specialised works.

To this effect, the works are expected to enable the two units to operate at full generation capacity once completed, with the exercise expected to be completed by December 2026.

EGENCO has assured the nation that it will continue addressing the challenges with urgency and determination by working to restore affected generation units and strengthen the reliability of Malawis power supply.

 

Tags: EgencoESCOM
ShareTweetShareSend
Previous Post

NOCMA loses K700m to email scam

Mana

Mana

Please login to join discussion

Sponsored

Twitter Handle

Tweets by MalawiAtlas

About Us

The Atlas is one of Malawi’s most established, reliable and impartial publications, that does not subscribe to the principles of any political party or pressure group. It takes a no-holds-barred approach in its reporting and strives to always keep authorities and others involved in public initiatives on their toes.

At The Atlas, we believe in and fervently pursue ethical journalism, and we resist any attempt to tilt our work towards interests of particular individuals or entities.

Follow Us

Trending this week

High Court rebuffs government in MEC relocation case

by Chancy Namadzunda
August 21, 2026
0

...

Court awards shop assistant K3.3m in overtime claim

Court awards shop assistant K3.3m in overtime claim

by Contributor
August 20, 2026
0

...

Recent Posts

EGENCO allocates USD8.1m towards addressing power generation challenges 

EGENCO allocates USD8.1m towards addressing power generation challenges 

by Mana
August 24, 2026
0

...

NOCMA loses K700m to email scam

NOCMA loses K700m to email scam

by Chancy Namadzunda
August 24, 2026
0

...

  • Home
  • Contact Us
  • Privacy Policy

© 2026 The Atlas Malawi -All Rights Reserved

No Result
View All Result
  • Home
  • National
  • Education
  • Health
  • Features
  • Politics
  • News
    • Business
  • Entertainment
  • Sports

© 2026 The Atlas Malawi -All Rights Reserved